Challenge
- Precast planks received a rough-screed concrete topping
- Topping required self-leveling course to make a flat and smooth surface
- Fast – track schedule with a two – week deadline
General Contractor
Newport Square NJ Construction, Jersey City, NJ
Architect
Poskanzer Skott Architects, Ridgewood, NJ
Installer
A-Deck, Inc., Norristown, PA
Situation
The building’s precise location is very unique, about twelve feet above the ground, on top of a stone embankment.
Solution
To accommodate the required project schedule, A-Deck was able to level 25,000 ft2 at approximately 1/2” per mobilization, pumping ARDEX V 1200™ 75’ vertically and 400’ horizontally. The CUBE® is capable of pumping up to 24,000 pounds / 12,000 ft2 at 1/4” per hour.